Self-Test D-2.4 Organizing a Plumbing Project
Complete Self-Test D-2.4 and check your answers.
- What is the first step in project planning for plumbing projects?
- Developing a schedule
- Defining the project scope
- Estimating costs
- Procuring materials
 
- In addition to a building’s shape and appearance, what do construction drawings focus on?
- Materials used
- Electrical layout
- Dimensions
- HVAC system
 
- Which document generally takes priority if there is a contradiction between construction drawings and specifications?
- Construction drawings
- Specifications
- Inspection reports
- Contractor notes
 
- The sequence of operation in plumbing projects typically requires how many phases of AHJ inspection?
- 1
- 2
- 3
- 4
 
- In project prioritization, tasks that MUST be done today are marked with a(n) ______.
- A
- B
- C
- D
 
- Who is responsible for proper site coordination in construction projects?
- Subcontractors
- General contractor
- Client
- Equipment suppliers
 
- What is the materials take-off list used for?
- Scheduling work phases
- Ordering materials
- Assigning workers
- Conducting inspections
 
- What is one advantage of renting equipment for a plumbing project?
- Lower long-term costs
- Immediate availability
- No maintenance responsibility
- Increased project speed
 
- Which of the following is a strategy to minimize inventory investment?
- Buying all materials in bulk
- Just-in-time delivery
- Storing materials off-site
- Using only high-cost materials
 
Answer Key: Self-Test D-2.4 is on the next page.